MahaRERA Registration Timeline: What Happens Week by Week, From Documents to Certificate
"How long will MahaRERA registration take?" is the first question every builder asks. The RERA Act gives MahaRERA 30 days to grant or reject a registration application (Section 5), but that clock assumes a complete application. In practice the time depends mostly on how ready your file is before you submit, and how quickly you answer scrutiny queries. Here is a realistic week-by-week plan for a project in Pune or PCMC with its approvals in place.
Before you start: what must already exist
A commencement certificate and sanctioned plans for the buildings you will register
Clear title, with every landowner, development agreement and power of attorney registered
Three project bank accounts opened in one scheduled bank. See the three accounts rule
Promoter KYC: PAN, firm or company documents, and details of past projects
If any of these is missing, fix it first. No amount of follow-up speeds up a registration that is waiting for a CC or a registered agreement.
Week 1: Collect and cross-check documents
Gather the 7/12 extracts or property card, mutation entries, title deeds, CC, plans, development agreement and encumbrance details. Then cross-check them: the same survey numbers, the same names, the same areas everywhere. Most scrutiny queries start with a mismatch someone could have caught in week 1. Use our documents checklist.
Week 2: Certificates and drafts
The Legal Title Report in Format A from your advocate
Certificates from the architect, engineer and CA on estimated costs and the project position
The proforma agreement for sale and allotment letter in the MahaRERA format. See Order 38/2022
A realistic proposed completion date. Choose it carefully: missing it later means an extension application with buyer consent.
Week 3: Portal entry and filing
Enter the project details, the building-wise inventory with carpet areas that match the plans, amenities, the professionals on the project and the bank accounts. Upload the documents, pay the registration fee and submit.
Weeks 4 to 6: Scrutiny and queries
MahaRERA checks every application at three levels, legal, technical and financial, through separate teams, and verifies the CC with the planning authority. Expect queries. Each query and reply adds time, so answer within a day or two with exactly what was asked, and keep the reply consistent with the rest of the file. A clean file can get through with few or no queries.
Registration certificate
Once approved, the registration certificate and project QR code are issued and the project page goes live. Only now can you advertise, book and sell.
What slows registration down
Title gaps: an old mutation entry, a missing heir, an unregistered agreement
A CC that does not cover all the buildings or floors in the application
Carpet areas in the inventory that differ from the sanctioned plans
Pending QPRs or Form 5 on the promoter's other projects
Slow replies to queries, or replies that raise new questions
The first 90 days after registration
Every ad carries the registration number and QR code.
Buyer payments go to the collection account only.
No more than 10% is taken before a registered agreement for sale.
The first QPR is due within 20 days of the end of the quarter. See QPR due dates.
Want a timeline for your project?
Send us your CC and 7/12 and we will tell you what is ready, what is missing and how long registration should take. Rohinee Engineers has handled MahaRERA work for 1,500+ projects over 8+ years from our office in Pimple Saudagar, Pune. See our MahaRERA services, run the free MahaRERA project check, or WhatsApp us on +91 89995 29930.