MahaRERA Agreement for Sale and Allotment Letter: Non-Negotiable Clauses for Advocates (Order 38/2022)
Every MahaRERA project registration includes the promoter's draft agreement for sale and allotment letter. These drafts are usually prepared by the builder's advocate, and they are one of the places where registrations get stuck. MahaRERA expects them to follow the model formats under the Maharashtra RERA Rules, 2017, and it has said clearly which clauses cannot be changed.
This guide is for advocates who draft these documents for builders, and for builders who want to know why their draft came back.
The starting point: the model agreement
The Maharashtra RERA Rules, 2017 prescribe a model agreement for sale. A promoter can add project-specific clauses, but the clauses that come from the Act, the Rules and the Regulations have to stay. Under Section 13 of the RERA Act, a promoter cannot take more than 10% of the cost of a flat as an advance without first signing and registering an agreement for sale.
MahaRERA Order No. 38/2022
In Order No. 38/2022, dated 13 December 2022, MahaRERA noted that many promoters were uploading agreement formats that departed from the model agreement. The order requires the mandated clauses to be kept as they are, and it names two clauses as strictly non-negotiable:
Variation in carpet area, and what happens to the price if the final carpet area differs from the agreed area.
Termination for payment default, including the promoter's obligation to refund the allottee.
Terms that contradict these clauses are treated as void and do not bind the allottee.
Deviations MahaRERA commonly flags
A force majeure clause widened beyond what the Act allows.
Timelines for forming the society or association of allottees that do not match the statutory timeline.
Delay in executing the conveyance deed.
A defect liability period that is shortened or left out.
MahaRERA has also directed that any deviation from the model agreement be highlighted in a different colour in the draft uploaded with the registration application. A deviation that conflicts with the Act can lead to the application being rejected.
The model allotment letter
When a promoter collects a deposit or advance of up to 10% of the flat cost, the allotment letter must be issued in MahaRERA's model format. Builders' own allotment letter templates, often older than RERA, are a frequent reason for a query.
Checklist before the draft is uploaded
Start from the current model agreement, not an older project's draft.
Keep the carpet area and termination clauses exactly as in the model.
Highlight every deviation in a different colour.
Match project details in the agreement with the registration application: promoter name, land description, carpet areas and completion date.
Use the model allotment letter for bookings up to 10%.
Check that the agreement's description of the land matches your Legal Title Report.
For advocates: how we work with you
We check your draft agreement and allotment letter against the registration data before filing and send any MahaRERA query on these documents straight back to you with exactly what was asked. You keep the drafting. We handle the portal and the follow-up. Rohinee Engineers has filed 1500+ MahaRERA projects from Pimple Saudagar, Pune over 8+ years. See all our MahaRERA services, run the free MahaRERA project check, or WhatsApp us on +91 89995 29930.
Related: MahaRERA registration for redevelopment projects and how to register a project under MahaRERA.
This guide is general information, not legal advice. Check the current text of MahaRERA orders before relying on it.