MahaRERA This Month: October 2026 Update for Builders, Architects and Advocates

Oct 30
3 min read

A short monthly summary of what changed around MahaRERA and what it means for builders, architects and advocates in Pune and PCMC. This edition covers October 2026.

1. 435 projects approved before Diwali, Pune leads with 140

MahaRERA approved 435 new housing projects worth about Rs 23,719 crore ahead of the festive season, with 32,981 apartments between them. Pune district had the most new registrations in the state at 140, and the wider Pune region 167. In the same round MahaRERA granted 210 extensions and approved 609 correction applications. Between April and September 2026 it processed 6,486 applications and issued 2,056 new registration numbers.

What it means: clean files are moving. If your registration, extension or correction is stuck, the cause is usually a query on your side of the file, not a queue at MahaRERA.

2. Four-month extension under Order 66/2026

On 7 August 2026, following a central advisory of 31 July, MahaRERA extended registration and completion timelines by four months for registered projects whose completion date (original, revised or extended) falls on or after 28 February 2026. Projects registered on or after 1 August 2026 are excluded. The extension is automatic.

What it does not change: it moves the date on the MahaRERA register only. Possession dates in your agreements for sale, interest payable to buyers for delay, and your lender's covenants stay as they were. Do not tell buyers that possession has moved by four months. If your project needs more time than this, plan a regular extension application early.

3. Sub-registrars told to check documents before registering sales

A revenue department circular of 12 October 2026, as reported, directs sub-registrars to refuse registration of first-sale agreements, sale deeds and other transfer documents where required documents are missing, or where the flat area is more than the sanctioned plan allows. For MahaRERA-registered projects, the registration certificate and sanctioned plan are to be checked, and an occupancy certificate may also be asked for. The circular has not yet been published in full.

What it means: the carpet area in every agreement must match the sanctioned plan and your MahaRERA inventory. If plans were revised, file the correction before registering agreements for the changed flats. Advocates: check this before the buyer reaches the registry office. See agreement for sale under Order 38/2022.

4. MahaRERA dues are now recovered faster

Revenue department guidelines reported in late August treat MahaRERA recovery warrants as priority cases, with dedicated recovery officers in Mumbai, Thane, Pune and other districts. The recovery certificate reaches the tehsildar within seven days, the demand notice allows 14 days to pay, and property can then be attached and auctioned. An unpaid MahaRERA order is no longer something that can wait.

5. Orders and rulings worth knowing

  • Pune, delay interest: MahaRERA ordered the developer of a Pune project to pay interest to eight buyers from 1 May 2026 until possession is offered, rejecting the argument that delays in government approvals excused the late possession.

  • Bombay High Court, refunds: in Sanklecha Constructions v. Nitin Shewale, the court held that a buyer's right to a refund with interest under Section 18 cannot be put off until the occupancy certificate is obtained.

6. Dates to keep

  • The July to September 2026 QPR was due on 20 October 2026. If it is still pending, file it now, before a notice arrives. See how to reply to a show-cause notice.

  • The October to December 2026 QPR is due by 20 January 2027. Start collecting Forms 1, 2 and 3 in the first week of January. See QPR due dates 2026-27.

  • If the Form 5 annual audit for 2025-26 is still pending, file it with the next QPR. See Form 5.

  • Launching after Diwali? Check every ad against the QR code and registration number rules.

Want this update every month?

We publish "MahaRERA This Month" at the end of every month for our builder, architect and advocate clients. Rohinee Engineers has handled MahaRERA work for 1,500+ projects over 8+ years from our office in Pimple Saudagar, Pune. See our MahaRERA services, run the free MahaRERA project check, or WhatsApp us on +91 89995 29930 to be added to the list.

Recent Posts

See All
महारेरा QPR तारखा 2026-27 आणि कारणे दाखवा नोटीस: बिल्डरांसाठी मराठी मार्गदर्शन

महारेरा QPR कधी भरायचा, चुकल्यास काय होते आणि कारणे दाखवा नोटीसला उत्तर कसे द्यावे: पुणे आणि PCMC मधील बिल्डरांसाठी सोप्या मराठीत.

 
 
 

Comments


bottom of page