MahaRERA Project Extension: 51% Allottee Consent, Documents and Process

Oct 25
2 min read

Construction often runs past the completion date on the MahaRERA registration certificate. When it does, the registration must be extended before it lapses. With a lapsed registration you cannot legally advertise or sell, and the project can be flagged for action.

When do you need a MahaRERA extension?

If the project will not receive its Occupancy Certificate by the completion date declared at registration, apply for an extension. Start at least three months before expiry, because collecting allottee consent and revised certificates takes time.

If you already have the OC, you usually do not need an extension. You file project completion (Form 4) instead.

The 51% allottee consent rule

Under MahaRERA Order 40/2022, an extension application must include written consent from at least 51% of the project's allottees, in the prescribed format. If you cannot get 51%, you can still apply, but you must submit the consents you do have, explain why the rest could not be obtained, and give a note on why the extension should be granted anyway.

Supplementary Order 40A/2023 added two more requirements: a list of complaints filed against the project before MahaRERA or any court, with the orders passed, and a notarised declaration that allottees' rights will not be affected.

Documents usually required

  • Extension application with the prescribed fee

  • Allottee consent letters, or the explanation above

  • Revised architect, engineer and CA certificates showing work and financial progress

  • Reasons for the delay, with supporting records

  • Updated schedule with the new completion date

  • List of complaints and the notarised declaration

  • All pending QPRs filed, because scrutiny often stalls when quarterly updates are missing

Why extension applications get stuck

  • Pending QPRs or Form 5 for earlier years

  • Consent letters in the wrong format or unsigned

  • Certificate figures that do not match earlier QPRs

  • A weak explanation for the delay

MahaRERA updates these rules through new orders, so confirm the current requirements before filing. We track every order as part of our work.

Need an extension filed?

Rohinee Engineers handles MahaRERA extensions for builders in Pune, PCMC and across Maharashtra, from consent formats to scrutiny replies. Use our free project check to see how many days your registration has left, or WhatsApp us on +91 89995 29930.

Recent Posts

See All
महारेरा QPR तारखा 2026-27 आणि कारणे दाखवा नोटीस: बिल्डरांसाठी मराठी मार्गदर्शन

महारेरा QPR कधी भरायचा, चुकल्यास काय होते आणि कारणे दाखवा नोटीसला उत्तर कसे द्यावे: पुणे आणि PCMC मधील बिल्डरांसाठी सोप्या मराठीत.

 
 
 

Comments


bottom of page