MahaRERA Project Extension: 51% Allottee Consent, Documents and Process
Construction often runs past the completion date on the MahaRERA registration certificate. When it does, the registration must be extended before it lapses. With a lapsed registration you cannot legally advertise or sell, and the project can be flagged for action.
When do you need a MahaRERA extension?
If the project will not receive its Occupancy Certificate by the completion date declared at registration, apply for an extension. Start at least three months before expiry, because collecting allottee consent and revised certificates takes time.
If you already have the OC, you usually do not need an extension. You file project completion (Form 4) instead.
The 51% allottee consent rule
Under MahaRERA Order 40/2022, an extension application must include written consent from at least 51% of the project's allottees, in the prescribed format. If you cannot get 51%, you can still apply, but you must submit the consents you do have, explain why the rest could not be obtained, and give a note on why the extension should be granted anyway.
Supplementary Order 40A/2023 added two more requirements: a list of complaints filed against the project before MahaRERA or any court, with the orders passed, and a notarised declaration that allottees' rights will not be affected.
Documents usually required
Extension application with the prescribed fee
Allottee consent letters, or the explanation above
Revised architect, engineer and CA certificates showing work and financial progress
Reasons for the delay, with supporting records
Updated schedule with the new completion date
List of complaints and the notarised declaration
All pending QPRs filed, because scrutiny often stalls when quarterly updates are missing
Why extension applications get stuck
Pending QPRs or Form 5 for earlier years
Consent letters in the wrong format or unsigned
Certificate figures that do not match earlier QPRs
A weak explanation for the delay
MahaRERA updates these rules through new orders, so confirm the current requirements before filing. We track every order as part of our work.