MahaRERA QPR Due Dates 2026-27 and What Happens If You Miss One

Oct 25
2 min read

If you are a builder with a MahaRERA-registered project, the Quarterly Progress Report (QPR) is the filing most likely to land you in trouble. In May 2026, MahaRERA issued show-cause notices to 8,212 projects across Maharashtra for missed QPRs, and 2,311 of them were in the Pune region. Most of those builders were not hiding anything. They simply missed a date.

This guide lists every QPR due date for 2026-27, what the report contains, and what to do if you have already missed one.

What is a MahaRERA QPR?

A QPR is the quarterly update a promoter uploads on the MahaRERA portal for every registered project until the project gets its Occupancy Certificate (OC) and is marked completed. Under MahaRERA Order 33/2022 it covers:

  • Construction progress, certified by the project architect (Form 1) and engineer (Form 2)

  • Money collected from allottees and how it was used, certified by a chartered accountant (Form 3)

  • Units booked and sold, and the amount received

  • Any change in approvals, plans or litigation

MahaRERA QPR due dates for 2026-27

MahaRERA expects each QPR within 20 days of the end of the quarter:

  • October to December 2026: due by 20 January 2027

  • January to March 2027: due by 20 April 2027

  • April to June 2027: due by 20 July 2027

  • July to September 2027: due by 20 October 2027

The certificates take time to collect, because your architect, engineer and CA each need site and account data. Start at least two weeks before the deadline.

What happens if you miss a QPR?

MahaRERA has moved from reminders to enforcement. Depending on how far behind a project is, builders have faced:

  • A show-cause notice with a deadline to file and reply (60 days in the May 2026 round)

  • Penalties on top of the filings still owed (press reports cite Rs 50,000 per project in recent rounds)

  • A ban on advertising, marketing and selling units

  • Freezing of the project's designated bank account

  • The registration being placed in abeyance or cancelled

For a project that is still selling flats, the sales ban and the frozen account hurt far more than the fine.

Received a MahaRERA notice for missed QPRs? Do this

  1. Check on the portal exactly which quarters are pending.

  2. Collect Forms 1, 2 and 3 for every pending quarter, not just the latest one.

  3. File all pending QPRs before replying, so the reply shows the default is cured.

  4. Send a short reply with the filing acknowledgements and the reasons for the delay.

  5. Put every future deadline on a calendar with a reminder three weeks ahead.

Check your project in one minute

Our free MahaRERA project check shows which QPRs and Form 5 filings your project owes, based on your registration date, and gives you a 12-month compliance calendar.

Rohinee Engineers has handled MahaRERA filings for 1,500+ projects over 8+ years from our office in Pimple Saudagar, Pune. If you have pending QPRs or a notice, WhatsApp us on +91 89995 29930 and we will tell you what is pending and what it takes to clear it.

Recent Posts

See All
महारेरा QPR तारखा 2026-27 आणि कारणे दाखवा नोटीस: बिल्डरांसाठी मराठी मार्गदर्शन

महारेरा QPR कधी भरायचा, चुकल्यास काय होते आणि कारणे दाखवा नोटीसला उत्तर कसे द्यावे: पुणे आणि PCMC मधील बिल्डरांसाठी सोप्या मराठीत.

 
 
 

Comments


bottom of page