Plotted Development and NA Plots on MahaRERA: Registration, Completion and Sales

Oct 30
3 min read

Plotted layouts around Pune, in belts like Chakan, Talegaon, Maval, Mulshi and Shirur, are often sold as "just NA plots, no construction". Many sellers assume RERA does not apply. It usually does. Under Section 2(zn) of the RERA Act, a real estate project includes developing land into plots for sale, and MahaRERA has repeatedly acted against plot sellers who advertised without registration.

When a plotted project needs registration

The same Section 3 tests apply as for buildings: registration is needed unless the land is 500 sq.m. or less, or the number of units is eight or fewer across all phases. Most plotted layouts are far above the land limit, so they must be registered before they are advertised, marketed, booked or sold. If your layout is small, check with us before you decide it is exempt.

What counts as the commencement certificate

A planning authority does not issue a building commencement certificate for a plot layout. MahaRERA Order 37/2022 clarified that for plotted development, the NA permission and sanad issued under the Maharashtra Land Revenue (Conversion of Use of Land and Non-Agricultural Assessment) Rules, 1969 are treated as the commencement certificate. Where a planning authority has approved the layout, that approval is needed as well.

What completion means for a plotted project

NA permission comes with conditions: internal roads, water supply, drainage, electricity and open spaces. The project is complete only when those conditions are met. Once they are, the promoter informs the Tahsildar, with Form 4 signed by the project architect, and uploads it to close the project on MahaRERA. MahaRERA has held that NA conversion is only the start of the process, and that the project is complete when the Tahsildar records that all the conditions are fulfilled. See our guide to project completion and Form 4.

Documents for a plotted project

  • 7/12 extracts, mutation entries and the title documents for every survey number

  • NA order and sanad, and the approved layout plan showing plot numbers, plot areas, roads and open spaces

  • A Legal Title Report covering all the land in the layout

  • Development agreement and power of attorney if the landowner is someone else. See joint development on MahaRERA

  • Cost estimates and a schedule for roads, water, drainage and electricity

  • The three project bank accounts in one scheduled bank

  • Architect, engineer and CA certificates

Mistakes that lead to notices

  • Advertising NA plots on social media, hoardings or WhatsApp before registration. Once registered, every ad needs the registration number and QR code.

  • Selling plots on sale deeds while the roads and services are still incomplete, then treating the project as complete.

  • Promising a clubhouse, compound wall or garden that is not in the approved layout.

  • Skipping QPRs because there is no building. The roads, drainage and services are the construction, and QPRs are due every quarter until completion.

For architects and engineers

On a plotted project your Form 1 and Form 2 report progress on the infrastructure works, and your Form 4 is the document that closes the project. Keep the progress figures consistent with the CA's Form 3. See MahaRERA Forms 1, 2 and 3.

Planning a plotted layout near Pune?

We register plotted projects, keep the QPRs going and close them properly with the Tahsildar intimation and Form 4. Rohinee Engineers has handled MahaRERA work for 1,500+ projects over 8+ years from our office in Pimple Saudagar, Pune. See our MahaRERA services, run the free MahaRERA project check, or WhatsApp us on +91 89995 29930.

Recent Posts

See All
महारेरा QPR तारखा 2026-27 आणि कारणे दाखवा नोटीस: बिल्डरांसाठी मराठी मार्गदर्शन

महारेरा QPR कधी भरायचा, चुकल्यास काय होते आणि कारणे दाखवा नोटीसला उत्तर कसे द्यावे: पुणे आणि PCMC मधील बिल्डरांसाठी सोप्या मराठीत.

 
 
 

Comments


bottom of page