Under Section 4(2)(l)(D) of the RERA Act, 70% of the money a promoter collects from allottees must sit in a separate project account. It can be withdrawn only in proportion to the work completed, and that proportion has to be certified by an architect, an engineer and a chartered accountant in practice. In Maharashtra those three certificates are Form 1, Form 2 and Form 3.

This guide is for architects, engineers and CAs who sign these forms, and for builders who need them to agree with each other.

Form 1: Architect's certificate

Form 1 certifies how much of the work is complete, building by building or wing by wing, against the approved plans. It also covers the progress of the layout and common amenities. It is signed by an architect registered with the Council of Architecture.

Form 2: Engineer's certificate

Form 2 certifies the cost of construction incurred so far and the estimated cost to complete the project. It is signed by a practising engineer, usually the project's site or structural engineer.

Form 3: Chartered accountant's certificate

Form 3 brings the numbers together. Using the land and construction cost, the percentage of completion and the money collected from allottees, the CA certifies how much the promoter can withdraw from the designated account. It is signed by a practising chartered accountant.

When these forms are needed

  • At every withdrawal from the designated account. Under MahaRERA Circular No. 39/2021 the promoter gives Forms 1, 2 and 3 to the bank for each withdrawal and uploads copies on MahaRERA.

  • With the quarterly progress report (QPR), so the project's public page shows current progress. See our QPR due dates for 2026-27.

  • At completion, when the architect issues Form 4, the completion certificate, along with the occupancy certificate.

  • Every financial year, when a CA audits the project account in Form 5.

These certificates are visible to anyone who opens the project on the MahaRERA website, including buyers and banks.

Where certificates go wrong

  • Form 1 shows 60% completion while Form 2 shows cost incurred closer to 30%, and Form 3 is worked out on yet another figure.

  • Progress is certified for a wing or floor that the commencement certificate does not yet cover.

  • The certificate date falls outside the quarter being reported.

  • A building is certified as a single unit when it was registered wing by wing.

  • The same certificate is reused across quarters with only the date changed.

MahaRERA treats these as professional certifications. An incorrect certificate is a problem for the professional who signed it, not only for the promoter.

How we work with architects, engineers and CAs

Each quarter we prepare one data sheet for the project with building-wise progress, costs and collections, so all three certificates are worked out from the same numbers before anyone signs. Then we upload them, file the QPR and track the project until the next deadline. Architects and CAs we work with tell us it saves them the back-and-forth with the builder's office.

Need help with MahaRERA certificates or QPRs?

Rohinee Engineers is a MahaRERA consultant in Pimple Saudagar, Pune, with 8+ years and 1500+ projects filed. See all our MahaRERA services, check what your project owes with the free MahaRERA project check, or WhatsApp us on +91 89995 29930.