Joint Development and MahaRERA: Is the Landowner Also a Promoter?
Most projects in Pune and PCMC are not built on land the builder owns outright. The landowner signs a joint development agreement (JDA), or a development agreement with a power of attorney, and takes either a share of the flats (area share) or a share of the sale money (revenue share). Under MahaRERA that landowner is usually a promoter too, and that changes who discloses what, who sells, and who is answerable to buyers.
Who is a promoter under RERA?
Section 2(zk) of the RERA Act defines the promoter widely. Its explanation says that where the person who builds and the person who sells are different, both are treated as promoters and are jointly responsible for the duties under the Act, the rules and the regulations. In 2017 MahaRERA clarified by circular that landowners and investors who are entitled to a share of revenue or a share of area in a project fall within the definition of promoter, and must be shown in the project registration.
Area share and revenue share
Area share: the landowner gets specific flats or shops. Those units are part of the project inventory on MahaRERA and are marked as the landowner's share. When the landowner sells them, the buyer is an allottee with the same RERA rights as any other buyer, so the same agreement format, disclosures and advance limits apply.
Revenue share: the landowner gets a percentage of collections while the developer sells all the units. The landowner is still a promoter for the purposes of the Act.
What changes in the MahaRERA registration
The landowner's details and the nature of their entitlement are disclosed in the application.
The registered development agreement and power of attorney are uploaded.
The Legal Title Report covers the landowner's title and the development rights that flow from it to the developer.
The unit inventory shows which units belong to the landowner's share, and the carpet areas match the approved plans.
Declarations and documents may need the landowner's signature, so plan the landowner's time before you file.
Liability: why joint matters
Buyers can hold both the developer and the landowner-promoter responsible for delay, defects and refunds. Appellate decisions have held that one promoter cannot escape a refund just because the buyer paid the other one. Your JDA can split responsibilities between the two of you, but that split binds only the two of you, not the buyers.
Common problems in JDA projects
Area sharing in the JDA does not match the inventory uploaded on MahaRERA.
The landowner sells their flats on a different agreement format that misses the clauses MahaRERA requires. See our guide to the agreement for sale and allotment letter.
Landowner signatures are missing when the file is ready, which delays registration, extension or correction applications.
A dispute between landowner and developer reaches court and shows on the project page as litigation, where buyers and banks can see it.
The developer is replaced midway without MahaRERA approval. See change of promoter on MahaRERA.
For advocates drafting JDAs
Draft the JDA with RERA in mind. Say clearly that the landowner is a promoter where they share revenue or area, who signs agreements for the landowner's units, who files QPRs and the annual Form 5, how the project bank accounts are operated, and who bears penalties for defaults caused by each party. A clean JDA makes both the title report and the registration simple. More notes for advocates are in our MahaRERA for Advocates section.
Related guides
Registering a joint development project?
We set up JDA projects on MahaRERA so the landowner share, inventory, title report and bank accounts all match from day one. Rohinee Engineers has handled MahaRERA work for 1,500+ projects over 8+ years from our office in Pimple Saudagar, Pune. See our MahaRERA services, run the free MahaRERA project check, or WhatsApp us on +91 89995 29930.