MahaRERA Project Completion: Form 4, OC Upload and Closing Your Project
A building can be finished, occupied and handed over, and still show as "ongoing" or "lapsed" on MahaRERA. Until completion is recorded on the portal, the project keeps owing quarterly progress reports, and once its completion date passes it is treated as lapsed. In December 2024 MahaRERA issued notices to more than 10,000 lapsed projects across the state. A finished building where completion was never recorded is treated the same way.
This guide explains what completion means on MahaRERA, what you need, and where it gets stuck.
What "completion" means on MahaRERA
Completion is recorded when the promoter uploads the Occupancy Certificate (OC) from the planning authority together with the architect's Form 4, the certificate of completion. Both are needed. MahaRERA has held that a Form 4 on its own, without an OC, does not amount to legal completion of the project.
Documents you need
Occupancy certificate (full, or part OC for the buildings it covers)
Form 4 signed by the project architect
All QPRs filed up to date
Form 5 annual audit reports filed for past financial years
Updated sales and inventory details on the portal
Pending QPRs are the most common blocker. MahaRERA restricts other services, such as correction and extension, until the QPR backlog is filed, so clear it first. See MahaRERA QPR due dates and Form 5 annual audit.
What if the OC came after the completion date?
This is common. If the completion date on your registration has already passed and the OC was issued later, the project will have shown as lapsed in between. MahaRERA allows the promoter to apply for correction of the completion date so the record matches the OC. If the OC is still pending and the date is close, apply for an extension before it expires instead.
Part OC and phase-wise projects
If you have an OC for only some buildings or wings, how completion is recorded depends on how the project was registered: as one project, or phase by phase. Get this checked before you upload anything, because a wrong upload can show the whole project as complete while some wings are still under construction and selling.
MahaRERA now verifies OCs
MahaRERA has started writing to planning authorities such as PMC, PCMC and PMRDA to confirm that uploaded OCs were actually issued and match the sanctioned plans. An OC that does not match the registered plans, unit count or promoter name will raise questions.
For architects: before you sign Form 4
The OC covers the same buildings and wings you are certifying.
Floors and unit numbers match the last approved plans on MahaRERA.
Any plan revision after registration was filed as a correction.
Your last Form 1 progress figures lead naturally to 100%.
See our guide to MahaRERA Forms 1, 2 and 3.
Close your project properly
Rohinee Engineers handles MahaRERA completion for builders across Pune and PCMC: we clear pending QPRs and Form 5s, coordinate Form 4 with your architect, upload the OC and follow up until the project shows as complete. 8+ years, 1500+ projects, Pimple Saudagar office. Run the free MahaRERA project check, see all our MahaRERA services, or WhatsApp us on +91 89995 29930.