Change of Promoter on MahaRERA: Section 15, Two-Thirds Consent and the Process
Projects change hands. A developer runs short of money, a partner exits, a society terminates one developer and appoints another, or a bigger builder takes over a stalled site. On MahaRERA none of this is a private deal. Section 15 of the RERA Act says a promoter cannot transfer or assign its majority rights and liabilities in a registered project to a third party without two approvals.
The two approvals under Section 15
Prior written consent of two-thirds of the allottees, not counting the promoter itself.
Prior written approval of MahaRERA.
The new promoter then has to meet every pending obligation of the old promoter, under the Act and under the agreements already signed with buyers. The transfer does not give the new promoter extra time: the completion date stays the same, and delay has the same consequences as before.
How the MahaRERA process works
MahaRERA set out the procedure in Circular 24/2019, later clarified by Circular 24A/2021:
Collect written consent from at least two-thirds of the allottees as on the date of the application.
Apply to MahaRERA in the prescribed format, with the consents, the agreement between the old and new promoter, and the new promoter's documents.
MahaRERA's legal wing examines the application and may call a hearing.
MahaRERA passes an order approving the change, with or without conditions, or rejecting it. The circular aims for a decision within one month of filing.
After approval, the promoter details, bank accounts and documents on the project page are updated to the new promoter.
When two-thirds consent may not be needed
A proprietor's business passing to legal heirs by succession.
A change in the form of the same promoter, such as a partnership becoming an LLP, has been treated differently from a transfer to an outsider. Check your case before you assume it is exempt.
The Bombay High Court has held, in the Tuvin Constructions case, that a new developer appointed by a society after terminating the earlier developer does not need the consent of two-thirds of the earlier developer's allottees to register with MahaRERA.
Grey areas to discuss with your advocate
A change in shareholding of the promoter company. Section 15 speaks about the project, not the company's shares.
A lender enforcing its security and taking over the project.
Transfer of only one building or phase of a larger project.
Mistakes that delay approval
Counting consents wrongly: cancelled bookings, the promoter's own units, or joint buyers counted twice.
Consent letters that do not name the new promoter or the terms of the transfer.
Pending QPRs or Form 5. MahaRERA expects these to be up to date before it processes other applications, so file them first. See QPR due dates and Form 5.
The new promoter's bank accounts and Legal Title Report not ready when MahaRERA approves.
A completion date that has already passed. The project may need an extension as well.
For advocates
The transfer agreement, the consent letter format and the new promoter's title chain all end up in front of MahaRERA. Draft the consent letter so each allottee confirms the new promoter's name and that their agreement continues on the same terms. Our notes for advocates are in the MahaRERA for Advocates section, including joint development and landowner promoters.
Taking over or handing over a project?
We prepare the consent tracker, the application and the post-approval portal changes, and clear pending QPRs first so the file is not held up. Rohinee Engineers has handled MahaRERA work for 1,500+ projects over 8+ years from our office in Pimple Saudagar, Pune. See our MahaRERA services, run the free MahaRERA project check, or WhatsApp us on +91 89995 29930.