Redevelopment is now a large part of construction in Pune and PCMC. Old housing societies are rebuilt, the members get new flats, and the builder funds the work by selling the extra flats. Those extra flats are why MahaRERA comes in. Here is what builders, societies and their advocates need to know before the first sale flat is advertised.

Does a redevelopment project need MahaRERA registration?

Yes, if there is a sale component. MahaRERA's order of December 2021 on redevelopment projects says the sale component has to be registered under Section 3 of the RERA Act before the promoter can advertise, book or sell. The flats given back to existing members, the rehab component, are not sold and are generally not treated as part of what needs registration. They still appear in the application, because the plans and the building cover both.

The usual thresholds apply: a project on more than 500 sq.m. of land, or with more than 8 apartments, has to be registered. Small redevelopments can fall below that, but check the numbers with us before you decide you are exempt.

Documents specific to redevelopment

  • A society resolution or NOC confirming the promoter's right to redevelop.

  • The registered development agreement with the society, and the power of attorney.

  • A commencement certificate that covers the sale component.

  • Approved plans showing rehab and sale areas separately.

  • A Legal Title Report covering the society's title to the land.

  • The standard registration documents. See our MahaRERA documents checklist.

How rehab and sale flats show on the portal

The inventory on MahaRERA has to separate rehab flats from sale flats, and the carpet areas must match the approved plans. Only sale flats are offered for booking. If the plan is revised later, for example to add floors, the change usually needs a correction application.

Where redevelopment registrations get stuck

  • Conveyance not done: many older Pune societies never got conveyance of the land. Without it, the title report cannot show the society as owner, and registration stalls until deemed conveyance is sorted out.

  • Partial commencement certificate: a CC up to plinth, or one that leaves out the sale floors.

  • Society consent: a resolution that does not reflect all members, or members who dispute it.

  • Area mismatch: the area sharing in the development agreement does not match the plans and the application.

For advocates and architects on redevelopment projects

Advocates: the title report has to cover the society's title and the development agreement together, and name the society correctly as landowner. Architects: Form 1 progress should cover the rehab and sale portions of the same building, since both are built together. See our guide to MahaRERA Forms 1, 2 and 3.

Planning a redevelopment project?

Our team regularly speaks on redevelopment in Pune, including the guest session "Redevelopment: The Next Decade of Construction in Pune" by Vishal Badgujar. Rohinee Engineers has filed 1500+ MahaRERA projects from our Pimple Saudagar office. See our MahaRERA services, run the free MahaRERA project check, or WhatsApp us on +91 89995 29930.

Recent Posts

See All
महारेरा QPR तारखा 2026-27 आणि कारणे दाखवा नोटीस: बिल्डरांसाठी मराठी मार्गदर्शन

महारेरा QPR कधी भरायचा, चुकल्यास काय होते आणि कारणे दाखवा नोटीसला उत्तर कसे द्यावे: पुणे आणि PCMC मधील बिल्डरांसाठी सोप्या मराठीत.

 
 
 

Comments


bottom of page